Tenative demolition/decontaimination timeline for the Frisco Exide plant
-
Dec. 31: Tentative date to begin demolition
-
Jan. 15: Tentative date to begin removal of plant’s smokestacks
-
March 1: Anticipated date to complete demolition
-
May 1: Anticipated date to complete remediation of land purchased by city of Frisco
-
Beyond May 1: Meet actions required by regulatory agencies